Home > Council and Democracy > Issue


Issue - meetings

TALBOT GATEWAY PHASE 3

Meeting: 25/02/2019 - Executive (Item 10.)

10. TALBOT GATEWAY OFFICE ACCOMMODATION pdf icon PDF 230 KB

To consider and discuss next steps in the Talbot Gateway project.

 

The report for this item is public. However Appendices 10a, 10b, 10c and 10 d contain information regarding the negotiations and the proposed or potential courses of action and are currently exempt from publication by virtue of Paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972. It is considered on balance that the public interest would not be served by publishing the information as it could prejudice the proposed development.

 

 

Additional documents:

Decision:

The Executive resolved as follows:

 

1.         To agree that Appendix 10a Assessment of Options, Appendix 10b Proposal Document to Potential Occupier, Appendix 10c Plan of Options and Appendix 10d Legal and Financial Considerations, to the Executive report, are not for publication by virtue of Paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972.

 

2.         To authorise expenditure to the sum of up to £1,250,000 to carry out concept and initial designs for the most appropriate option to meet this future potential demand.

 

3.         To delegate authority to the Chief Executive to authorise expenditure and contracts to produce concept and initial designs within the financial limit agreed in 1 and the detailed estimates in Appendix 10d, to the Executive report.