WINTER GARDENS SPANISH HALL ROOF AND CORONATION STREET FACADE

Decision Maker: Executive

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

To consider the authorisation of £1,995,000 expenditure and the associated funding package in order to carry out priority works to the Coronation Street façade and Spanish Hall roof of the Winter Gardens complex.

 

Subject to authorisation, the funding package for the priority works will include £895,000 Prudential Borrowing and £600,000 Corporate allocation from the Council’s Capital Programme provided over two financial years 2017/18 and 2018/19, in addition to £500,000 grant funding.

 

Decision:

The Executive agreed the recommendations as outlined above namely:

 

  1. That expenditure of £1,995,000 is authorised in order to carry out priority repairs to the Coronation Street façade and Spanish Hall roof of the Winter Gardens complex. 

 

2.      That Prudential Borrowing of £895,000 and a £600,000 Corporate allocation from the Council’s Capital Programme provided over two financial years 2017/18 and 2018/19 is authorised in order to fund priority repairs to the Coronation Street façade and Spanish Hall roof of the Winter Gardens complex. 

Publication date: 14/03/2017

Date of decision: 13/03/2017

Decided at meeting: 13/03/2017 - Executive

Effective from: 18/03/2017